Public Participation / Consultation in the EIA Process

Public participation is an important aspect of the EIA process in Sri Lanka. The provision for public participation is contained in the National Environmental Act (NEA).


Once an EIA report is submitted the National Environmental Act provides for public inspection and comment on the EIA report during a mandatory period of 30 days. EIA reports are available for perusal by the public in Sinhala, Tamil and English. These reports are usually kept for public inspection in the CEA Headquarter Library, the relevant Divisional Secretariat Office and PradeshiyaSabha. Any member of the public may send their comments to the Central Environmental Authority or the respective Project Approving Agency, within 30 working days. The Project Approving Agency (PAA) publishes notices in the National Newspapers inviting the public to inspect and comment on the EIA report within 30 days. The notice specifies where and when the EIA report can be inspected. The public have a right to obtain copies of the EIA report from the PAA by paying copying charges. A public hearing may also be held at the discretion of the PAA when it is thought that it would be in the public interest to do so.

The public comments received must be sent to the project proponent for response. The project proponent must respond to comments by making every effort to improve the project.

The IEE reports are not required to open for public comments for a mandatory period of 30 days. However, an IEE report shall be deemed to be a public document and shall open for inspection by the public.

In addition to the above mandatory requirement, the project proponents are always advised to have informal dialogues / consultation with the local people during the EIA study. The project proponent must ensure that the local people get accurate information about the project. If the local community is negatively affected by the project, it is important that the project proponent consult them and obtain their support in proposing mitigation measures to minimize the impacts.     

Last Updated on Monday, 26 August 2013 11:47

infoactEng

polythene copy copy

neweco

manu

ngoenglish

ReEBwaste

 lastepa

 epayment

weerawila

Latest News & Events

  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
Banned Polythene Raiding Continues…………. Manufacturing, trading and usage of any kind of... Read more
E – Friends ii , Revolving Fund loans for Eco friendly Entrepreneur Budget 2018 proposed to implement the “Pavithra Ganga”... Read more
Polythene Raiding at Piliyandala & Rathmalana The Central Environmental Authority continually conducts... Read more
Two-day Workshop for the Environmental Officers of CEA - Group III A two-day workshop for the Environmental Officers of the... Read more
Festival Season, Eco program at the Gregory Lake Considering the upcoming festival season in April, the... Read more
Residential Training for EPP Commissioners To encourage and strengthen the Environmental Pioneer... Read more
Continue raids on banned polythene products The Central Environmental Authority and the Environmental... Read more
Mr. Chandrarathne Pallegama Appointed as New Chairman of the CEA Mr. Chandrarathne Pallegama appointed as the new Chairman... Read more
CEA New Year Festival -2018 The annual New Year festival of the Environmental... Read more
Vesak Lantern Competition Parallel to the National Vesak Festival the Welfare... Read more
New Office for CEA Northern Province Office By spending of 56 million rupees CEA established a new... Read more
Workshop on Technical challenges for Sustainable Development To enhance the knowledge of environmental conservation... Read more